The terminal Brest (where most of the transshipment operations are being done due the optimized infrastructure) is divided in 3 main parts: one section for transshipment of covered railroad cars, a section for open-top cars, and a container section.
Detailed information to the container section:
Track number 9 crane runway, 8520 m. in area
• Capacity 1435 gauge: 40 wagons
• Capacity 1520 gauge: 20 wagons
• Storage capacity 2 tiers: 80 (40ft)
• Processing capacity: 240 wagon with containers
• Availability of gantry cranes with a trestle span of 16 m: KK-6,3; KK-16/20; MKKS-42 (total: 3)
• Volume processed in 2013: 271,100 t.
• Temporary storage warehouse (type A), 11,252.3 m. in area
• Length of track: 630 m
• Capacity 1435 gauge: 42 wagons
• Capacity 1520 gauge: 42 wagons
• Storage capacity 1 tier: 336 containers (40ft) or 672 containers (20ft)
• Storage capacity 2 tiers: 672 (40ft) or 1344 (20ft)
• Processing capacity of containers/day: 342
• Access ways for trucks